U.S. Highway 14 - From Philip East Eight Miles

Project Summary:
This project will replace three structures, two box culverts, and construct one new bridge.
Approach grading and pipe replacement will also be included on the project.
Traffic is rerouted around the work area using the temporary diversions so crews can conduct structure and grading work. Traffic diversions will remain in place for the majority of the 2024 construction season. The first phase of work is expected to be completed on Friday, Oct. 25, 2024, with work resuming in spring 2025.
Project Timeline:
March 18, 2024 - Nov. 2025
Project Updates:
April 22, 2025:
March 15, 2025 – April 15, 2025, Completed Work: The contractor began their 2025 construction season placing riprap at the east bridge (site 3), six miles east of Philip. They have also begun preparation for the diversion for site two, approximately three miles east of Philip.
Anticipated work April 15, 2025 – May 15, 2025: The contractor will complete the diversion at site two, approximately three miles east of Philip so traffic can begin to go around the remaining project construction site. The existing structure at site two will begin to be removed.
---
Dec. 2, 2024:
Oct. 15, 2024 – Nov. 15, 2024, Completed Work: Grading and pipe installation at the sites located one and one-half miles and four and one-half miles east of Philipis near completion. Construction on the box culvert located one and one-half miles east of Philip was completed. Construction on the bridge located four and one-half miles east of Philip was completed. Erosion control work was mostly completed on the sites one and one-half miles and four and one-half miles east of Philip. Class HR paving was completed on the sites one and one-half miles and four and one-half miles east of Philip.
Anticipated work Nov. 15, 2024 – Dec. 15, 2024: General project cleanup will continue on the project. Guardrail installation and permanent pavement markings will be installed. The project will be opened up to through traffic. Work will commence next spring.
Project Photos:
Project Contract Amount:
$16.7 Million
Project Contacts:
SDDOT:© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic