S.D. Highway 46 - From Beresford to Iowa State Line
Project Summary:
This project is a fifteen-and-one-half mile-long full reconstruction of S.D. Highway 46 in Union and Lincoln Counties. The project begins at the east edge of the city of Beresford and ends at the Iowa state line. Work on this project will consist of full roadway grading, structure replacement, culvert replacement, interim surfacing, and new permanent signing.
Construction is broken into three phases and covers two construction seasons.
Phase one starts at the east edge of Beresford and ends at the S.D. Highway 11/S.D. Highway 46 intersection. Work in phase one will be completed during the 2024 season with an interim completion date of Nov. 2024.
Phase two will be from the Highway 11/ Highway 46 intersection to the Hudson curve.
Phase three will be completed under traffic from the Hudson curve to the Iowa state line. Phase two and three will be completed during the 2025 construction season.
During construction, the highway will be closed to through traffic. Access to residents and landowners adjacent to the project will be maintained, but travelers are encouraged to use the signed detour route around the project. The detour route around the project for phase one includes Interstate 29 to Lincoln County 152 and Highway 11. Phase two detour includes Highway 11 to Lincoln Co 152 and Lincoln Co 143. Phase three will be completed under traffic using temporary widening.
Sign Up for Text Notifications:
For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time.
Text BERESFORD46 to 605-566-4041
Project Timeline:
Spring 2024 - Nov. 2025
Project Updates:
Oct. 27, 2025:
Sept. 15, 2025 – Oct. 15, 2025, Completed Work:
Grading and gravel surfacing have been completed from 482nd Avenue to the Hudson curve. Grading of the east half of Phase 3, from the curve to the Iowa line, is also complete, and gravel surfacing has begun. All pipe culverts have been installed. Interim surfacing has been completed from 482nd Avenue to the new alignment of 297th Street at the Hudson curve.
Anticipated Work Oct. 15, 2025 – Nov. 15, 2025:
The contractor will complete gravel surfacing on Phase 3 and apply interim surfacing, weather permitting. Erosion control will be finished for the remainder of the project, and permanent signing and pavement markings will be installed.
Project Detour Maps:
2025 Phase Two Detour Map:
Click to enlarge
Project Photos:
Project Contract Amount:
$24.8 Million
Project Contacts:
SDDOT:© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic