Highway 52 Grading Project from Tabor to Springfield Delayed
For Immediate Release: Thursday, February 27, 2020
Contact: Rod Gall or Greg Rothschadl 605-668-2929
SPRINGFIELD, S.D. – South Dakota Department of Transportation officials say the reconstruction of Highway 52 from Tabor to Springfield will be delayed from a 2020 construction year to 2021.
The delay is due to the Highway 37 shoulder widening project north of Springfield that was unable to be finished in 2019 due to wet weather and will be completed in 2020. Highway 37 will be the main detour route during the Highway 52 construction project.
Some minor work on the Highway 52 project may be done in late 2020, but should have minimal impact to motorists.
For complete road construction information, visit https://www.safetravelusa.com/sd/ or dial 511.
- 30 -
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic