Interstate 29 Bridge Rehabilitation Sioux Falls - Over Skunk Creek
Project Summary:
Interstate 29 north and south - approximately ½ mile north of 26th Street over Skunk Creek, over 12th Street (exit 79), approximately ½ mile north of 12th Street over Ellis & Eastern Railroad.
- Bridge Deck Overlay
- Approach Slabs
- Guardrail
Sign Up for Text Notifications:
For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time.
Text I29Bridges to 605-566-4041
Project Timeline:
Spring 2025 - Fall 2025
Project Updates:
April 17, 2025:
On Monday, April 21, 2025, work is scheduled to begin on the Interstate 29 southbound structure over Skunk Creek in Sioux Falls. On Wednesday, April 23, 2025, the east two lanes of southbound I-29 will be closed for crews to complete the work. Traffic on I-29 will be maintained in the west two lanes. Weather dependent, this traffic configuration is anticipated to be in place until Friday, June 13, 2025.
Once work is complete, traffic will be switched to the newly constructed east two lanes of I-29 at 26th Street. Work will then begin in the west two lanes at this location.
---
April 16, 2025 - Press Release:
On Monday, April 21, 2025, work is scheduled to begin on the northbound structure on Interstate 29 over Skunk Creek in Sioux Falls. For this structure work, the northbound on-ramp at 26th Street will be closed as work is completed on the east two lanes of I-29. Traffic on I-29 will be maintained in the west two lanes. This traffic configuration and northbound on-ramp closure at 26th Street is anticipated to be in place until Friday, June 13, 2025.
Once work is complete, traffic will be switched to the newly constructed east two lanes on I-29 at 26th Street. Work will then begin in the west two lanes on I-29 at 26th Street.
---
April 2, 2025 - Press Release:
On Monday, April 7, 2025, work will begin on the Interstate 29 northbound structures over 12th Street and the Ellis & Eastern Railroad tracks.
Traffic control will be in place closing the east two lanes. Traffic will be maintained on the two west lanes. This configuration will continue until Wednesday, May 21, 2025, when traffic will be switched to the newly constructed east lanes. Crews will then begin work on the adjacent two lanes on the west side.
Project Photos:
Project Contract Amount:
$7.4 Million
Project Contacts:
SDDOT:Brad Tiede
605-367-5680
Contractor:
General Excavating LLC.
STATEWIDE CONSTRUCTION PROJECTS PAGE
PCN: 065E
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic
Region & Area Offices
Travelers
© 2025 State of South Dakota. All Rights Reserved.
Becker-Hansen Building
700 E. Broadway Ave.
Pierre, SD 57501
Modern Logic