Interstate 90 and I-29 and I-229 Bridges in Sioux Falls

SiouxFallsBridges.png

Project Summary:

Interstate 90 East and West - Interstate 90 and Interstate 29 Interchange over I-29 drainage ditch and I-90/I-229 Interchange over I-229

  • Bridge Deck Overlays
  • Approach Slabs PCC Pavement
  • Signing and Guardrail

Sign Up for Text Notifications:

For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time. 

Text I90Bridges to 605-566-4041

Project Timeline:

April 2025 - Fall 2025

Project Updates:

June 2, 2025:

On Tuesday, June 3, 2025, improvements to the westbound Interstate 90 bridge over Interstate 229 will begin. Crews will be placing traffic control to allow for two-way traffic on eastbound I-90 and closing the north loop ramps of the I-90 and I-229 interchange, exit 400.

Two-way traffic on eastbound I-90, along with the loop ramp closures, will be in effect from Thursday, June 5 until Friday, July 11, 2025.

---

May 20, 2025: 

April 15, 2025 – May 15, 2025, Completed Work: The contractor has completed the low slump and bridge approaches for the eastbound I-90 structure over I-29. 

Anticipated work in May 15, 2025 – June 15, 2025: The contractor plans to complete all concrete paving, asphalt shoulders, guardrail, and membrane seals for the eastbound I-90 structure over I-29. Once these items are complete, they will open to traffic including the south loop ramps. Remaining work may include lane closures on the eastbound structure over I-29. 

---

April 3, 2025 - Press Release: 

On Monday, April 7, 2025, work will begin on the Interstate 90 eastbound structure over Interstate 29. Traffic control will be put into place to allow for a two-way traffic configuration on westbound I-90 utilizing crossovers. The south loop ramps of the I-90 and I-29 interchange will be closed during this time. This two-way traffic configuration is scheduled to begin on Monday, April 14, 2025, and continue until Saturday, May 10, 2025.


Project Photos:


Project Contract Amount:

$3.1 Million

Project Contacts:

SDDOT: 
Brad Tiede
605-367-5680


Contractor:
Journey Group Companies

STATEWIDE CONSTRUCTION PROJECTS PAGE

 

 

PCN: 091T