S.D. Highway 13 Near Elkton

Elkton.png

Project Summary:

S.D. Highway 13 - From S.D. Highway 324 to U.S. Highway 14

  • Shoulder Widening
  • Resurfacing
  • Approach Grading
  • Pipe Work
  • New Signal

Project Timeline:

April 2025 - November 2025

Project Updates:

July 22, 2025: 

June 15, 2025 – July 15, 2025, Completed Work: The contractor nearly finished all grading operations on the east and west section of S.D. Highway 13. They also started grading operations on the north and south section of S.D. Highway 13, as well as began pipe replacement for pipe going under S.D. Highway 13. Work has also begun on the structure removal on the north/south section of S.D. Highway 13.  

Anticipated work July 15, 2025 – Aug. 15, 2025: The contractor will continue grading on the north and south sections as well as completed the pipe work on the east and west section of S.D. Highway 13. The contractor will also remove the existing structure on the north/south stretch of S.D. Highway 13 and begin to install the new structure. 

---

April 30, 2025 - Press Release: 

Construction Work has begun on S.D. Highway 13 from the intersection of S.D. Highway 324 toward the city of Elkton. Work on the project will include shoulder widening, asphalt concrete resurfacing, pipe work, grading and structure replacement. Lane closures will be in place for the project during the day. Traffic will be guided through the work zone with flaggers and a pilot car. Motorists should be prepared for delay through the work zone. 

As part of this reconstruction project, Highway 13 is closed north of Elkton to U.S. Highway 14. A signed detour route is in place to guide traffic around the closed portion of Highway 13 using local roadways.

 

Project Photos:


Project Contract Amount:

$8 Million

Project Contacts:

SDDOT: 
Thomas Lindstrom
605-881-7137


Contractor:
R and G Construction Co. 
507-537-1473