S.D. Highway 15 - From Clear Lake South to S.D. Highway 28


Project Summary:

This project consists of grading and widening to improve road smoothness and sight distance to increase safety.

There will be an interim surface of gravel and asphalt throughout the winter of 2024-2025 with a paving project to follow in July of 2025 through Aug. 2025. 

Project Updates:

Aug. 22, 2025: 

July 15, 2025 – Aug. 15, 2025, Completed Work:

Paving work began August 6 and is expected to continue through the end of August, weather permitting.

Anticipated Work Aug. 15, 2025 – Sept. 15, 2025:

After paving is completed, crews will finish the project with rumble striping and pavement markings.

Project Photos:

 

Project Contacts:

SDDOT: 
Bryce Olson
605-882-5166


Contractor:
Bowes Construction of Brookings, SD