U.S. Highway 12 - Between Aberdeen and Mina

4.png
Project Summary:

This project consists of a bridge replacement over Snake Creek. 


Traffic on Highway 12 will be directed to use the on-site diversion around the project area.  

Project Timeline:

April 2025 - Nov. 2025

Alternate Route:

mina-detour.png

Project Updates:

May 20, 2025: 

April 15, 2025 – May 15, 2025, Completed Work: Crews installed erosion protection and demolished center/west portion of bridge, including center piles. 

Anticipated work in May 15, 2025 – June 15, 2025: The contractor plans to set the west sheet pile and dewater. They will also drive west abutment piles as well as excavate and place west bank protection. 

 

Project Photos:

Project Contract Amount:

$5.7 Million

Project Contacts:

SDDOT: 
Robert Ward
605-626-7885

Contractor: 
RR Schroeder Construction, Inc.of Glenwood, MN.