U.S. Highway 12 - Bridges Near Keldron and McIntosh

PROJECT COMPLETE



Project Summary:

This project on U.S. Highway 12 replaces two aging bridges over the BNSF Railroad. The new, wider bridges are located approximately one and one-half miles west of Keldron and one mile east of McIntosh.


Project Timeline:

April 15, 2024 - Nov. 2024
*Remaining work for spring of 2025 includes erosion control, guardrail rework, and bridge punch list items.

Project Updates:

Dec. 20, 2024:

Oct. 15, 2024 – Nov. 15, 2024, Completed Work: Guardrail has been installed at McIntosh site. 

Anticipated work Nov. 15, 2024 – Dec. 15, 2024: Guardrail installation at Keldron site as well as erosion control and miscellaneous bridge punch list work remains at both sites. 

 

Project Photos:


Project Contract Amount:

$14.4 Million