S.D. Highway 1889 - Euclid Ave
Project Updates:
Feb. 25, 2026:
The S.D. Highway 1889 (Euclid Avenue) urban reconstruction project within the city of Pierre is scheduled to begin its second year of construction. Weather dependent, work is scheduled to begin as follows:
Beginning the week of March 2, 2026:
• Euclid Avenue from Wynoka Street to Elizabeth Street
Traffic will be adjacent to construction work from March 2 through March 9, 2026. The week of March 9, 2026, this segment will be closed for reconstruction until the anticipated reopening in late July 2026.
• Wynoka Street from Evans Street to Euclid Avenue
New storm sewer installation will continue. Traffic will be shifted to accommodate construction work.
Beginning the week of March 9, 2026:
• Euclid Avenue from 4th Street to north of 8th Street
Two-way traffic will be adjacent to construction work for the entirety of the 2026 construction season.
• Elizabeth Street from east of Grand Avenue to Euclid Avenue
This segment will be closed to accommodate new city water and sewer, and then reconstruction of the street, with an anticipated reopening in late July 2026.
As these segments are completed, work will advance into other segments of the Euclid Avenue reconstruction project. A 10-foot width restriction will be in effect for the entirety of the construction season when a two-way traffic condition exists. During the closure of Euclid Avenue from Wynoka Street to Elizabeth Street, over width and through vehicles will be detoured for the duration of the planned closure.
Pedestrians will be detoured through and around the work zones as needed. The traveling public is asked to be alert through the work zone for longer queues of traffic, construction vehicles entering and exiting the work zones, and for workers adjacent to moving traffic.
Feb. 11, 2026:
On Thursday, Feb. 19, 2026, the South Dakota Department of Transportation (SDDOT), in collaboration with the City of Pierre, and Morris, Inc., will hold an informational meeting to discuss the second year of reconstruction on Euclid Avenue in Pierre. The meeting, which will include construction timelines and traffic changes, is scheduled to begin at 6 p.m. at Faith Lutheran Church, located at 714 North Grand Ave. in Pierre. The informational meeting is designed to share project information and answer questions for members of the public including impacted residents, local businesses, and emergency service personnel.
A short presentation will be shared at 6 p.m. Members of the SDDOT, the City of Pierre, and Morris, Inc. will be available to discuss the project and answer questions.
Additional Resources:
View Weekly Meeting Minutes on Morris Inc. Website
View the City of Pierre's Website for Water Main Project Information
Project Summary:
Urban reconstruction, asphalt and concrete surfacing, storm sewer, lighting, signals, sanitary sewer and water main replacement.
-
U.S. Highway 14/83 (Euclid Avenue) – from Sioux Avenue intersection to the divided highway west of S.D. Highway 1804 in Pierre.
-
Elizabeth Street (between Highway 14 and Grand Avenue).
-
Wynoka Street drainage outfall.
Public Informational Meeting:
Past Meeting Information:
On Thursday, March 20, 2025, the South Dakota Department of Transportation (SDDOT), along with the City of Pierre, and Morris Inc., held a public informational meeting to discuss the upcoming Euclid reconstruction project in Pierre. The meeting, included construction timelines and traffic changes. Morris, Inc., the contractor for the Euclid Avenue reconstruction project, provided a short presentation at each meeting.
View the meeting presentation here
Sign Up for Text Notifications:
For updates on MAJOR traffic changes, subscribe to a free text-in service. To subscribe, simply text the keyword listed below to 605-566-4041. Subscribers can unsubscribe at any time.
Text EUCLID to 605-566-4041
Project Timeline:
Year One:
Spring 2025 - Fall 2025
Year Two:
Spring 2026 - Nov. 2026
Detour Map:
Project Photos:
Project Contract Amount:
$26.4 Million
Project Contacts:
SDDOT: Dean VanDeWiele